Testing Permissive Overreaching; Testing Blocking Scheme - ABB Relion 670 Series REL670 Commissioning Manual

Line distance protection 2.1 iec
Table of Contents

Advertisement

1MRK 506 355-UEN A
10.11.1.2
10.11.1.3
Line distance protection REL670 2.1 IEC
Commissioning manual
Testing functionality by secondary injection
5.
Check that other zones operate according to their zone timers and that the send
(CS) signal is obtained only for the zone configured to generate the actual signal.
6.
Deactivate the receive (CR) signal in the IED.
7.
Check that the trip time complies with the zone timers and that correct trip
outputs, external signals, and indications are obtained for the actual type of fault
generated.

Testing permissive overreaching

1.
Activate the receive (CR) signal in the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the permissive zone.
4.
Check that correct trip outputs, external signals, and indication are obtained for
the actual type of fault generated.
5.
Check that the other zones operate according to their zone timer and that the send
(CS) signal is obtained only for the zones that are configured to give the actual
signal. Also the zone connected to CS underreach is giving CS in this mode.
6.
Deactivate the IED receive (CR) signal.
7.
Apply healthy normal load conditions to the IED for at least two seconds.
8.
Apply a fault condition within the permissive zone.
9.
Check that trip time complies with the zone timers and that correct trip outputs,
external signals, and indications are obtained for the actual type of fault
generated.

Testing blocking scheme

1.
Deactivate the receive (CR) signal of the IED.
2.
Apply healthy normal load conditions to the IED for at least two seconds.
3.
Apply a fault condition within the forward directed zone used for scheme
communication tripping.
4.
Check that correct trip outputs and external signals are obtained for the type of
fault generated and that the operate time complies with the tCoord timer (plus
relay measuring time).
5.
Check that the other zones operate according to their zone times and that a send
(CS) signal is only obtained for the reverse zone.
6.
Activate the IED receive (CR) signal.
7.
Apply a fault condition in the forward directed zone used for scheme
communication tripping.
8.
Check that the no trip from scheme communication occurs.
9.
Check that the trip time from the forward directed zone used for scheme
communication tripping complies with the zone timer and that correct trip
outputs, external signals, and indications are obtained for the actual type of fault
generated.
Section 10
211

Advertisement

Table of Contents
loading

Table of Contents