Clearance Requirements for Airflow and Hardware Maintenance on MX104 Routers
Related
Documentation
Copyright © 2014, Juniper Networks, Inc.
When planning the installation site, allow sufficient clearance around the rack (see
Figure 13 on page
41):
For the cooling system to function properly, the airflow around the chassis must be
unrestricted. Allow at least 6 in. (15.2 cm) of clearance between side-cooled routers.
Allow 2.8 in. (7 cm) between the side of the chassis and any non-heat-producing
surface such as a wall.
For service personnel to remove and install hardware components, there must be
adequate space at the front and back of the router. At least 24 in. (61 cm) is required
both in front of and behind the router. NEBS GR-63 recommends that you allow at
least 30 in. (72.6 cm) in front of the rack and 24 in. (61.0 cm) behind the router.

Figure 13: MX104 Chassis Dimensions and Clearance Requirements

24" (61 cm)
clearance required
for maintenance
6"
(15.2 cm)
30" (72.6 cm)
clearance required
for maintenance
Preparing the Site for the MX104 Router Overview on page 37
Rack Requirements for MX104 Routers on page 38
Cabinet Requirements for MX104 Routers on page 39
Installing and Connecting an MX104 Router Overview on page 43
Chapter 4: Preparing the Site for MX104 Router Installation
Rear
17.22"
(43.7 cm)
9.4"
(24 cm)
19.2"
(48.7 cm)
Front
6"
(15.2 cm)
Front-
mounting
flange