Acceptance Checks
''Task 24: Test Local Area Network'' (optional).
''Task 25: Clear Administration, Error, and Alarm Logs'', if necessary.

Worksheets Needed

Before beginning these tasks, make sure you have the Administering Voice Ports
as Stations Worksheet — B-1 for Display Set or B-5 for Control Link — from
Planning for the DEFINITY AUDIX System , 585-300-601. The project manager
should have provided you with this worksheet.
Task 18: Alarm Origination
Administration/test and Status Tape
Worksheet C-10, Set Up Alarm Origination , indicates whether alarm origination is to be
activated through AUDIX only , through the switch only , or through both . If alarm origination
is to be set up through the switch only, rather than through AUDIX only or through both, skip
to step 9 of this task.
You will perform this task jointly with people at the INADS center.
The steps listed below present a typical execution of this task but you may vary the steps
for this site depending on the approach you agree upon with the INADS people.
1. Call INADS and request administration and test of alarm origination for this
DEFINITY AUDIX system.
2. If you have not already done so, log in to the DEFINITY AUDIX system terminal as
craft. (Refer to Task 14A: Set the DEFINITY AUDIX Clock for the login procedure.)
3. Type change system-parameters maintenance and press
4-2
Issue 2 December 1996
.
RETURN