Acceptance Checks

This chapter describes tests to ensure that the DEFINITY AUDIX System is
functioning properly after installation. Joint Acceptance Testing is used to ensure
that IMAPI is operational. These tests should be run with a customer LAN system
administrator.
Joint Acceptance Testing is required to be executed by both the customer and
the Lucent installer when the entire solution includes Lucent and customer-
provided equipment. Acceptance Testing is performed at the end of an
installation to demonstrate to the customer that the solution is operational for
customer use. The purpose of Joint Acceptance Testing is to have
knowledgeable people available to test and resolve issues before final
completion of the service order.

Acceptance Check Tasks

The acceptance-check tasks include:
''Task 18: Alarm Origination Administration/test and Status Tape'' (optional)
''Task 19: Perform Dial Tone Test for DS Integrated Systems''.
''Task 20: Run Test Switch-Link Long'' (Control Link only).
''Task 21: Add Two Test Subscribers''
''Task 22: Test the Call Answer and Voice Mail Features''
''Task 23: Run Test Tape Long''