Avaya Communication Server 1000M Series Upgrade page 139

Meridian 1 51c sg cp piv upgrade
Table of Contents

Advertisement

7
Test the clocks:
a.
Verify that the clock controller is assigned to the active Core:
LD 60
SSCK x
SWCK
****
8
Verify that the Clock Controllers are switching correctly:
SWCK
SWCK
9
Check applications.
10 Check dial tone.
Performing the upgrade
Load program
Get status of the clock controllers (x is "0" or "1"
for Clock 0 or Clock 1)
Switch the Clock (if necessary)
Exit program
Switch Clock
Note: You must wait a minimum of one minute for
clocks to synchronize.
Switch Clock again
End of Procedure
51C to CS 1000M SG CP PIV Upgrade
Page 139 of 198

Advertisement

Table of Contents
loading

This manual is also suitable for:

Cs 1000m seriesCs 1000m sgCs 1000m mg

Table of Contents