Test Core/Net 1
Procedure 29
Testing Core/Net 1
1
Check dial-tone.
2
Test the clocks:
a.
Verify that the clock controller is assigned to the active Core.
LD 60
SSCK x
SWCK
****
b.
Verify that the clock controllers are switching correctly.
SWCK
SWCK
****
3
Stat D-channels:
LD 96
STAT DCH
****
4
Stat all T1 interfaces:
LD 60
STAT
****
Performing the upgrade
Load program
Get the status of the clock controllers (x is "0" or
"1" for Clock 0 or Clock 1)
To switch the Clock (if necessary)
Exit program
Switch the Clock
Note: You must wait a minimum of one minute for
clocks to synchronize.
Switch the Clock again
Exit program
Stat all D-channels
Exit program
Stat all DTI and PRI
Exit program
51C to CS 1000M SG CP PIV Upgrade