8B - 6
BATTERY/STARTER/G EN ERATO R SERVICE
Fig. 15 Starter Remove/Install - V-6/V-8 Engine
(6) Reverse removal procedures to install. Tighten
starter hardware as follows:
B R
Fig. 16 Starter Terminal Connections - Diesel
Engine
© starter mounting bolts - 48 N-m (32 ft. lbs.)
• solenoid lead nut - 6 N-m (55 in. lbs.)
• battery lead nut - 10 N-m (90 in. lbs.).
STARTER RELAY REMOVE/INSTALL
(1) Disconnect battery negative cable(s).
(2) Remove starter relay by unplugging unit from
Power Distribution Center (PDC) (Fig. 18). Refer to
underside of PDC cover for relay location.
(3) Install starter relay by aligning relay terminals
with cavities in PDC and plugging relay in.
(4) Connect negative cable(s) to battery.
(5) Test relay operation.