Table 6-3 Software Requirements For Commissioning On Profinet Io; Commissioning And Startup Of Et 200S On Profinet Io - Siemens Simatic ET 200S Operating Instructions Manual

Distributed i/o system
Hide thumbs Also See for Simatic ET 200S:
Table of Contents

Advertisement

Commissioning
6.3 Commissioning on PROFINET IO
6.3.4

Commissioning and startup of ET 200S on PROFINET IO

Software Requirements
Table 6-3
Software requirements for commissioning on PROFINET IO
Configuration software
used
STEP 7
Configuration software for
a different IO controller
Requirements for commissioning
The following additional requirements must be satisfied for commissioning the ET 200S on
PROFIBUS IO:
• IO device installed
• IO device wired up
• IO device provided with device name
• Supply voltage for the DP master is switched on (see manual for the IO controller)
• IO controller is switched to RUN mode (see manual for the IO controller)
Commissioning the ET 200S
To commission the IO device, proceed as follows:
1. Switch on the power supply for the IO device.
2. If necessary, switch on the supply voltage for the load.
6-18
Version
Version 5.3 and higher and ServicePack 1 for
IM151-3 PN (6ES7151-3AA00-0AB0)
Version 5.3 and higher and ServicePack 3 for
IM151-3 PN (6ES7151-3AA10-0AB0 and higher)
and IM151-3 PN HIGH FEATURE (6ES7151-
3BA20-0AB0 and higher)
Notes
You use HW Config and the supplied
GSD file.
You need the GSD file of ET 200S.
Operating Instructions, 12/2005, A5E00515771-03
ET 200S