Commissioning and Diagnostics
6.2
Commissioning and startup of the ET 200S
Software requirements
Table 6-3
Software requirements for commissioning
Configuration
software used
STEP 7
COM PROFIBUS
Configuration software
for a different DP
master
Requirements for commissioning the ET 200S
Table 6-4
Requirements for commissioning the ET 200S
1st DP slave installed
2nd PROFIBUS address set on the DP slave
4. DP slave wired
5. DP slave configured (configured and parameters assigned)
6. Supply voltage switched on for DP master
7. DP master set to RUN mode
Commissioning the ET 200S
Table 6-5
Procedure for commissioning the DP slave
Step
1st
Switch on the supply voltage for the DP slave.
2nd
Switch on the supply voltage for the load as necessary.
6-10
Version
As of Version 5.0
You are using HW Config. As of ServicePack 3, the
and ServicePack 3
ET 200S is included in the hardware catalog.
As of Version 5.1,
You have integrated the device database file of ET 200S
ServicePack 2,
in COM PROFIBUS.
Hotfix 1
You need the device database file of ET 200S.
Required Activity
Procedure
Notes
See ...
Chapter 4
Section 4.8
Chapter 5
Section 6.1
DP master manual
DP master manual
See ...
Section 9.3
ET 200S Distributed I/O System
EWA-4NEB780602402-09