Mount the rack

The rack must be securely
mounted to the side of the
gate, it must be parallel with
the gate rail and there must be
a 2mm - 3mm gap between the
teeth of the pinion and the rack
along the entire travel of the
gate.
Follow this procedure whether mounting steel, RAZ or nylon angle rack
Refer to the sections that follow for specifics about the mounting of each type
of rack
1. Before mounting the rack, raise the
operator an additional 3mm.
2. Put the gearbox into Manual Mode.
Refer to Section 26 for complete
instructions.
Gate rail
Gate rail
page 30
Rack
parallel
to rail
3mm
tooth gap
FIGURE 35.
3mm
RAISE
FIGURE 36.
FIGURE 37.