Electrical Installation Of The Power Cabinet; General Procedure - ABB Terra HP Generation 4 CE Ionity Installation Manual

Table of Contents

Advertisement

7

Electrical installation of the power cabinet

7.1

General procedure

Preliminary requirements
Procedure
1. Open the door of the power cabinet. Refer to section 10.1.
2. Connect the PE wires to the power cabinet. Refer to section 7.2.
3. Connect the AC input cable.
a. Remove the AC cover. Refer to section 10.4.
b. Connect the AC input cable. Refer to section 7.3.
c. Install the AC cover.
4. Connect the AC auxiliary power, interlock and DC guard, and Ethernet cables.
a. Connect the AC auxiliary power cable. Refer to section 7.4.
b. Connect the interlock and DC guard cables. Refer to section 7.5.
c. Connect the Ethernet cable. Refer to section 7.6.
5. Close and lock the door of the power cabinet. Refer to section 10.5.
7.2
Connect the PE cable
Preliminary requirements
6AGA000032-0115-EN | 004
Note: For a detailed overview of all electrical connections, refer to
section 12.19.
The DC cables are
installed in one of the
cable conduits. Refer to
section 12.17.
The AC input cable,
the PE wire and the
communication cables are
installed in the other cable
conduits. Refer to section
12.17.
Wire stripper pliers
Wire cutter
Torque wrench
Cable lug
Fasteners M11
Electrical installation of the power cabinet
45

Advertisement

Table of Contents
loading

Table of Contents