Prepare A Metal Foundationfor The Charge Post; Prepare A Custom Foundation For The Charge Post - ABB Terra HP Generation 4 CE Ionity Installation Manual

Table of Contents

Advertisement

4.4.5
Prepare a metal foundation for the charge post
Preliminary requirements
A metal foundation is suitable if the power cabinet is installed on a solid floor and
you need to connect conduit pipes. Make sure that the metal foundation is attached
to the equipment enclosures and that the equipment enclosures are mounted to
the ground. For an overview and the specifications of the metal frame (A) for the
power cabinet, refer to section 12.16.2.
Procedure
1. Mark the position of the holes (B)
on the ground. For the specifications,
refer to section 12.15.2.
2. Drill and thread the holes. Do
not make holes in not authorized
locations. This may compromise the
structural integrity of the metal
foundation.
3. Drill the gland plate to allow the cable
conduits to pass through.
You can insert your own conduit knockouts, based on the shaded regions.
4. Guide the cables to the cable trays (C).
5. Align the metal frame (A) with the threaded holes. Make sure that the front of
the metal frame (D) is in the correct position.
6. Install the fasteners (E).
7. Tighten the fasteners to the correct torque. For the specification, refer to
section 12.13.
4.4.6

Prepare a custom foundation for the charge post

Preliminary requirements
6AGA000032-0115-EN | 004
Drill with screw tap
Torque wrench
For an overview of the cable
conduits, refer to section 12.15.2.
For the gland plates, refer to
section 3.5.8.
Custom foundation. Refer to section 12.16.7.
Pre-installation
Metal frame. Refer to
section 12.16.4.
If you have not included
the foundation in the
initial order, contact the
manufacturer to order the
foundation for your power
cabinet. Refer to section
1.12.
A
C
D
E
B
33