Figure 3-16 Installing an expansion bolt (unit: mm)
1.
2.
3.
4.
Step 3 Use a pallet truck to move the cabinet to the installation position.
Step 4 Secure the cabinet to the expansion bolt holes on the ground using M12x60
expansion bolts. The installation methods for different UPS models are the same.
Figure 3-17
Figure 3-17 Tightening expansion bolts
Step 5 Install the front, rear, left, and right anchor baffle plates. The installation methods
for different UPS models are the same.
baffle plates for a 400 kVA UPS cabinet.
Issue 12 (2023-05-26)
Drill holes in the ground by using a hammer drill. The hole depth is 52 mm to
60 mm.
Partially tighten the expansion bolt and vertically insert it into the hole. Knock
the expansion bolt using a rubber mallet until the expansion sleeve is fully
inserted into the hole.
Partially tighten the expansion bolt.
Remove the bolt, spring washer, and flat washer.
shows how to secure a 400 kVA UPS cabinet.