Installation steering guide
Illustration 2-1: Installation Flowchart with Ghost Load/ Load From Cold / Load From Warm
Start
Site configuration
forms completed
Y
Install
site monitor
configuration
A+ Monitor
A Monitor
B Monitor
Physical
Physical
Physical
Connection
Connection
Connection
IST 001
IST 002
IST 003
Software Installation
(Not needed for new installation)
SW001- Load from cold (Ghost)
SW002- Load from warm
Install any optional peripheral
device(s). See Table 2-1
Configure Centricity RA600 system
to site CNF001
Install & configure any peripheral
software. See Table 2-1
Calibrate Monitor(s) with
BARCO Tool - MediCal Pro
Software CNF 006
Functional Checks VF 001 and
Save System & User Settings VF 002
Customer Turnover
VF 003
Stop
Page 27
Complete site
N
configuration forms
IST 006
C Monitor
B+ Monitor
Physical
Physical
Connection
Connection
IST 005
IST 004
Install any software patch(es)
included with the RA600 application
SW014