Figure 75: Phase balancing using QD Cable phase rotation when using QD Cable QD-12-20-135 (7.9
Conclusion
As shown in the above example, when cable connectors are left unused on a three-phase system, it creates a phase
imbalance for the system with each phase (L1-L2, L2-L3, L3-L1) having different number of Microinverters.
If multiple cable connectors are skipped over multiple branch circuits, the imbalance can multiply.
Installation Guidelines:
Minimize the number of unused QD Cable connectors - You can avoid the skipping of the QD Cable connectors with
the use of 3 Phase Field wireable (QD-CONN-10F and QD-CONN-10M) connectors along with Raw QD Cable to extend
the cable drop length.
If the installation requires few connectors to be skipped during installations, it is recommended to make sure that
equal number of micros connected to C1(L1-L2), C2(L2-L3) and C3(L3-L1) type connectors.
If the number of Micros connected to C1, C2 and C3 type of connectors is not same, please refer to local AHJs rules
for acceptable phase imbalance across the system.
© 2022 Enphase Energy Inc. All rights reserved.
ft Cable), branch circuit of varied sizes and few skipped connectors
IQ8D-DG-MKT-00397-02-EN-US-2022-06-10