installation checklist

Perform a site inspection prior to the installation date to check existing site conditions and identify constraints and
limitations that could possibly cause delays or problems during the actual installation.
Site Accessibility
1. Verify existing loading facilities and proximity of loading dock to staging area.
2. Verify if receiving area is accessible by trailer.
3. Verify access to service elevators.
4. Reserve service elevators in advance, if necessary.
Site Preparation
1. Clear all obstacles that could interfere with the installation process.
2. When doing a reconfiguration, ensure that all furniture to be re-used are clear of computers, accessories,
books, papers and all personal effects.
3. Ensure that all live wires and data/communications wires are disconnected prior to installation.
Furniture Plans
1. Labeled furniture plans for installation purposes are located in the hardware box. Ensure that drawings are
complete and handy before beginning installation.
Waste Management
1. Establish a trash removal area separate from the product staging area.