Verifying Operation Of Zs5-4 Slide-Rails And Cma - Oracle ZFS Installation Manual

Hide thumbs Also See for ZFS:
Table of Contents

Advertisement

Verifying Operation of ZS5-4 Slide-Rails and CMA

4.
Install and route cables to the controller, as required.
If required, attach the cable hook and loop straps to the CMA, and press them
5.
into place to secure the cables.
Note -
to reinstall cable hooks and straps.
6.
For best results, place three cable straps (1), evenly spaced, on the rear-facing
side of the CMA arm (2), and three cable straps on the side of the CMA nearest
the controller.
Verifying Operation of ZS5-4 Slide-Rails and CMA
Use the following procedure to verify the operation of the CMA and slide rails for a ZS5-4
controller.
Ensure all rack anti-tilt devices are extended to prevent the rack from tipping forward when the
Before You Begin
storage controller is extended from the rack.
Slowly pull the storage controller out of the rack until the slide-rails reach their
1.
stops.
2.
Inspect the attached cables for any binding or kinks.
154
Oracle ZFS Storage Appliance Installation Guide, Release OS8.8.x • August 2021
Cable hooks and loop straps are preinstalled on the CMA. Perform this step if you need

Advertisement