MACHINE OPERATIONS AND CONTROLS
13. Before starting the work, check that fuel control dial (4) is
at a 2/3 position between Low idle (MIN) position and High
idle (MAX) position.
If it is not at a 2/3 position, set it to the 2/3 position and run
the engine at 2/3 speed between MIN and MAX before op-
erating.
14. Before starting actual work, repeat the following operation 3 to 5 times.
Circulate warm hydraulic oil through all control circuits.
•
Boom operation: RAISE (E) ←→ LOWER (F)
•
Arm operation: IN (B) ←→ OUT (A)
•
Bucket operation: CURL (D) ←→ DUMP (C)
•
Swing operation: LEFT (G) ←→ RIGHT (H)
When performing swing operations, release swing
lock switch (2), check that the swing lock pilot lamp is
OFF, then operate the swing.
•
Travel (Lo) operation: FORWARD (A) ←→ REVERSE
(B)
•
For attachment operations (if equipped), change the
working mode to the attachment mode.
3-184