Prerequisites - Cisco SRS Series Installation Manual

Cisco crs routers 16-slot line card chassis
Table of Contents

Advertisement

Prerequisites

Prerequisites
To ensure a satisfactory ground connection, you need the following parts:
• One grounding lug that has two M6 bolt holes with 0.63 inches (5/8 inch) (1.60 cm) of spacing center
Figure 11: 180-Degree (Straight) Chassis Ground Lug
Figure 12: 45-Degree Chassis Ground Lug
• Two M6 hex head bolts and integrated locking washers are pre-installed on the chassis.
Cisco CRS Routers 16-Slot Line Card Chassis Installation Guide
20
to center between them and a 6 AWG or larger multi strand copper wire. The grounding lug used can be
either a 180 degree (straight) lug or a 45-degree lug.
Installing and Removing Power Components

Advertisement

Table of Contents
loading

This manual is also suitable for:

Crs-16-lcc/mCrs-16lcc140/mCrs-16/s

Table of Contents