Parallel System Installation Checklist
Each cabinet in the parallel system is placed in its installed location.
All conduits and cables are properly routed to the UPSs and to the parallel tie cabinet.
All power cables are properly sized and terminated.
Neutral conductors are installed between cabinets as required.
Ground conductors are properly installed.
CAN wiring between the UPSs is properly installed.
Pull chain wiring between the UPSs is properly installed.
Adequate workspace exists around the UPSs, parallel tie cabinet, and other cabinets.
Startup and operational checks are performed by an authorised Eaton Customer Service Engineer, for parallel
systems.
Battery wire has correctly polarity and installation.
External battery breaker is off and can't be turned on as it is locked by UVT.
Warning label is paste on external battery breaker.
128