these requirements, the power connections must have the following characteristics:
• The installation must include a separate disconnect device, such as a switch or circuit breaker,
included as part of the building installation. The electrical specifications of this device must
accommodate the power and environmental requirements of the equipment for the particular
application.
• This device must be in close proximity to the equipment and within easy reach of an operator.
• This device must be permanently marked as the disconnect device for the equipment.
For hazardous location installations, read and follow the guidelines contained in the two para-
!
graphs below.
WARNING
For Zone 1 installations, no cable glands or strain reliefs are supplied with the system. Only remov-
able gland plates and junction boxes with threaded entries are provided. It is the customer's respon-
sibility to provide for the complete installation of this system. (Refer to the Specifications Section
and CD package.) This includes supplying and installing external fittings, cabling, strain reliefs,
suitable cable glands, etc. Only qualified personnel should perform this installation with adherence
to all the additional electrical and mechanical requirements for this type of installation and location.
For NEC Division 1 and 2 installations, the internal seal-offs or fittings are supplied in the system
but must be sealed by the customer before being put into service. All other external fittings, cabling,
conduit, etc. are the responsibility of the customer. (Refer to the Specifications Section and CD pack-
age.) Only qualified personnel should perform this installation with adherence to all the additional
electrical and mechanical NEC requirements for the installation type and location.
Procedure
The shielded interconnecting cable between the field unit and controller is already in place
with wires clearly identified at both ends
An AC power source of adequate current rating is available at both locations.
1.
Unscrew and remove the lid from 5000 Field Unit.
2.
Connect controller signal and alarm outputs to user recording equipment as shown i
in the CD package.
3.
Connect AC power source to:
Field Unit — TB1-1 AC line, TB1-2 AC Neutral, and GND to TB1-3 or to chassis ground stud.
Controller—TB5-1 AC line, TB5-2 AC NEUT, and GND lug. TB5-3 can be used to jumper line voltage
to Sample and Alarm Common.
4.
Instrument grounding is mandatory. Performance specifications and safety features are void
ated from an improperly grounded source. Check ground integrity to all portions of the
if unit is oper
analyzer before power up. See Fig. 5e for proper internal grounding instructions.
2-10 5000 Multi Point Moisture Analyzer