If the rack rail assemblies are in a new location or the old cage nuts have been
12.
removed, use either a tape measure or by counting holes in the rack posts insert
one of the supplied cage nuts into the left front rack post as shown in Figure
7-22.
Figure 7-22 Cage Nuts inserted into a Rack Post
Repeat the same procedure for the right front rack post making sure that the
13.
cage nut is at the same height as the left side.
The library is now ready to be placed back on the rack rail assemblies.
14.
Have two or more people lift the library by grabbing the front and rear hand
15.
holds as seen in Figure 7-23. Place it between the rack posts and slide it back on
the rack rails until about 8 inches remains sticking out the front of the rack
posts.
Front
Hand Holds
Figure 7-23 Library being inserted into the Rack
511010 Rev. 07-01-19
13.38
9.38
6.38
2.38
Field–Replaceable Units (FRUs)
Possible
Cage Nut
Locations
Rear
Hand Hold
7-27