3.3 IAC-D Cabinet Installation

The method used to install the IAC-D depends on the type of installation being
undertaken. The IAC-D can be installed as a line-up–and–match or standalone system. The
term line-up–and–match refers to cabinets that are physically attached to the UPS, and the
wiring between them is internal. The term standalone refers to cabinets that are not
physically attached to the UPS, and are wired with external contractor-supplied wiring.
3.3.1 Line-up–and–Match IAC-D Installation
Use this procedure to install the IAC-D adjacent to the Powerware 9390 UPS cabinet (see
Figure 3-3 or Figure 3-4). The recommended location is to the right of the UPS cabinet.
This procedure assumes the IAC-D is located to the right of the UPS cabinet.
EATON Powerware
9390 IAC-D Installation and Operation Manual S 164201591 Rev B powerware.com
®
To install a line-up–and–match IAC-D, proceed to paragraph 3.3.1.
To install a standalone IAC-D, proceed to paragraph 3.3.2.
Figure 3-3. 80 kVA UPS with Line-up–and–Match IAC-D
1. Verify that the UPS is properly installed and secured. Refer to the applicable
Powerware 9390 Installation and Operation manual, listed in paragraph 1.5, for
installation instructions.
2. Roll the IAC-D to an area near the right-hand side of the UPS.
Installing the IAC-D