Installing the IAC-D
Installation Checklist
- All packing materials and restraints have been removed from each cabinet.
- Each cabinet in the UPS system is placed in its installed location.
- Shipping brackets are installed on the cabinet and bolted to the floor for permanent installations.
- All conduits and cables are properly routed to the IAC-D.
- All power cables are properly sized and terminated.
- Distribution Panel branch circuit breakers are installed and wired to load. (OPTIONAL)
- If installed, Distribution Panel Input breaker current settings are correct.
- If installed, Distribution breaker current settings are correct.
- A ground conductor is properly installed.
- Air conditioning equipment is installed and operating correctly.
- The area around the installed UPS system is clean and dust-free. (The UPS and IAC-D must be installed on
a level floor suitable for computer or electronic equipment.)
- Adequate workspace exists around the IAC-D and other cabinets.
- Adequate lighting is provided around all UPS system equipment.
- A 120V service outlet is located within 25 feet of the UPS and IAC-D equipment.
- Startup and operational checks are performed by an authorized Powerware Customer Service Engineer.
3-15