Honeywell ControlEdge 900 platform Hardware Planning And Installation Manual page 218

Controledge plc, controledge rtu
Hide thumbs Also See for ControlEdge 900 platform:
Table of Contents

Advertisement

Appendix A - Installing RTP
2. Mount the RTP to the DIN rail.
3. Set switch positions SW1 through SW8. as shown.
4.
218
900RTC-H250 Remote Termination High Voltage Cable Assembly, 5.0
l
meters long
ATTENTION: Cable power is limited to 24 Amps per module at 60 C°
(140 degrees F) and 32 Amps at 54 C°(129 degrees F).
c. Install the module label onto the module connector cover.
d. Connect shield drain wire to the grounding bars at the base of the
ControlEdge 900 Controller rack. All field-wiring shields must be grounded
as described in the shield grounding section.
a. Secure the RTP to the rail. See "Securing the RTP to the DIN rail" on
page 228 for more information. for details.
b. Connect the cable to the RTP.
Module Removal / Insertion Under Power (RIUP) is supported by turning off
Switch SW1 to allow removal of the module from the rack without causing an
arc.
See "RTP Cable wire positions, colors, and internal schematic" on the facing
page for more information.
Connect field wiring.