a. Remove the relevant key tabs from the terminal block to allow connection
with the module.
b. Connect the appropriate cable to the module at ControlEdge 900
Controller. Possible options are:
900RTC-H210 Remote Termination High Voltage Cable Assembly, 1.0
l
meters long
900RTC-H225 Remote Termination High Voltage Cable Assembly, 2.5
l
meters long
900RTC-H250 Remote Termination High Voltage Cable Assembly, 5.0
l
meters long
c. Install the module label onto the module connector cover.
d. Connect shield drain wire to the grounding bars at the base of the
ControlEdge 900 Controller rack. All field-wiring shields must be grounded
as described in the shield grounding section.
2. Mount the RTP to the DIN rail.
a. Secure the RTP to the rail. See "Securing the RTP to the DIN rail" on
page 228 for more information. for details.