Honeywell ControlEdge 900 platform Hardware Planning And Installation Manual page 203

Controledge plc, controledge rtu
Hide thumbs Also See for ControlEdge 900 platform:
Table of Contents

Advertisement

900RTC-L225 Remote Termination High Voltage Cable Assembly, 2.5
l
meters long
900RTC-L250 Remote Termination High Voltage Cable Assembly, 5.0
l
meters long
c. Install the module label onto the module connector cover.
d. Connect shield drain wire to the grounding bars at the base of the
ControlEdge 900 Controller rack. All field-wiring shields must be grounded
as described in the shield grounding section.
2. Mount the RTP to the DIN rail.
a. Secure the RTP to the rail. See "Securing the RTP to the DIN rail" on
page 228 for more information. for details.
b. Connect the cable to the RTP.
3. Set/verify jumper positions as shown.
Module Removal / Insertion Under Power (RIUP) is supported by turning off
Switch SW1 to allow removal of the module from the rack without causing an
arc.
ATTENTION: SW1 only disconnects the positive terminal, not both sides
of the DC power.
See "RTP Cable wire positions, colors, and internal schematic" on page 1 for
more information.
4.
Connect field wiring.
Appendix A - Installing RTP
203

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents