3 Connect the GC end and the MSD end of the GC/MS interface cable.
_F"=©
GQ¬
mFO"4F
"*dF|
m=}
mFO"4F
p¦F
mFO"4F
"*dF| Fm=}
Qn
4 Carefully push the MSD and GC together.
When positioned properly, the end of the GC/MS interface cover will touch the
oven wall and the GC/MS interface tip will protrude slightly into the GC oven.
5 Connect the cables on the back of the MS.
— APG start/stop cable coming from the GC to the Remote connector
— LAN cable coming from the hub
— Rough pump power cable
6 Connect the MSD power cord to an appropriate ac outlet.
7 Remove the MSD analyzer cover.
8 Loosen the sideplate thumbscrews completely, disconnect the source
power and side board control cables, and open the analyzer.
9 Remove the interface column nut and blank ferrule from the GC end of the
GC/MSD interface.
2 Hardware Installation (Differences)
Connecting the MSD and the GC