PROCEDURES UP TO OPERATION
This chapter describes the procedures before operation.
1.
Check of FX5-DP-M specifications
Check the FX5-DP-M specifications. (Page 18 SPECIFICATIONS)
2.
Installation of FX5-DP-M
Install a FX5-DP-M to a CPU module. For details, refer to the following.
MELSEC iQ-F FX5U User's Manual (Hardware)
MELSEC iQ-F FX5UC User's Manual (Hardware)
3.
Wiring
Perform wiring of external devices to a FX5-DP-M.
4.
Adding a module
Add a FX5-DP-M to a module configuration by using GX Works3.
5.
Parameter settings
Set parameters of the FX5-DP-M by using PROFIBUS Configuration Tool and GX Works3.
6.
Programming
Create a program. (Page 94 PROGRAMMING)