Checkout Procedure; Required Tools/Special Equipment; Initial Power Up - GE Medical Systems Solar 9500 Service Manual

Information monitor
Table of Contents

Advertisement

Checkout Procedure

Required Tools/Special Equipment

Initial Power Up

6-18
Maintenance: Checkout Procedure
This procedure tests the functions of the monitor, Tram-rac housing and
associated communication networks. For the Tram module and input
modules checkout procedures, refer to their appropriate service manuals.
See the chart below for the equipment necessary to perform this checkout
procedure. Equivalent equipment may be substituted.
Item
Tram 100-850 module
BP module
Multifunctional Micro-simulator
Oscilloscope
Port Checkout DIDCA
AutoPort to M-Port adapter
Complete the following steps. Failure to attain any of the listed results
indicates a malfunction.
1. With AC switch OFF, check the line voltage configuration of the
Solar 9500 and attach the power cord to the appropriate line source.
2. Confirm that all components of the monitoring system are correctly
connected as described in chapter 3, Installation.
3. Power ON all devices and the Solar 9500 under test.
4. Verify that the AC LED on the front panel illuminates indicating the
power is ON. Also verify that the two fans inside the Solar 9500 are
running and that the CPU LED on the front panel illuminates,
indicating CPU activity.
5. Place the Tram module into the top two slots of the Tram-rac
housing. Verify that the power indicator illuminates.
6. Configure the monitor display with as many waveforms as possible.
Refer to the appropriate monitor operator's manual, if necessary.
7. The waveforms should look clean (no noise).
Solar 9500 Information Monitor
2001085-061
Manufacturer and Part Number/Model
GE any
GE any
MARQ-1
Tektronix 2215
420915-031
2001973-001
Revision A