Installation

6.1

General installation procedure

Preliminary requirements
Procedure
1. Do the mechanical installation of the power cabinet. Refer to section 6.2.
2. Do the mechanical installation of the charge post. Refer to section 6.3.
3. Do the electrical installation of the power cabinet. Refer to section 7.
4. Do the electrical installation of the charge post. Refer to section .
5. Prepare for commissioning. Refer to section
6.2

Mechanical installation of the power cabinet

6.2.1

Install the power cabinet - general procedure

Preliminary requirements
Procedure
1. Remove the plinth covers of the power cabinet. Refer to section 10.7.
2. Install the cabinet on the foundation. Refer to section 6.2.2.
3. Open the cable inlets. Refer to section 6.2.3.
4. Guide the cables to the power cabinet. Refer to section 6.2.4.
5. Close the cable inlets. Refer to section 6.2.5.
6. Install these parts:
a. Cover plate of the foundation. Refer to section 6.2.6.
b. Plinth covers of the power cabinet.
7. Replace the eye bolts on the power cabinet with the caps. Refer to section 12.2.
9AKK107992A2254-EN | 005
The AC input cable is
available.
The foundations for the
cabinet is prepared.
All cables are in the cable
conduits and the full cable
slack is applied.
The substation is
prepared.
The site is prepared.
Tools for installation. Refer
to section 12.3.
The cabinet is above the foundation.
There is no voltage on
the AC input cable during
the complete installation
procedure.