7 CALIBRATION

Notes.
• The analyzer is calibrated by the Company prior to dispatch and the Factory Settings pages are protected by an access code.
• Routine recalibration is not necessary – high stability components are used in the analyzer's input circuitry and, once
calibrated, the Analog-to-Digital converter chip self-compensates for zero and span drift. It is therefore unlikely that the
calibration will change over time.
attempt recalibration without first contacting ABB.
Do Not
attempt recalibration unless the input board has been replaced or the Factory Calibration tampered with.
Do Not
• Prior to attempting recalibration, test the analyzer's accuracy using suitably calibrated test equipment – see Sections 7.1
and 7.2.

7.1 Equipment Required

a) Decade resistance box (conductivity cell input simulator): 0 to 10k (in increments of 0.1), accuracy 0.1%.
b) Decade resistance box (Pt100/Pt1000 temperature input simulator): 0 to 1k (in increments of 0.01), accuracy 0.1%.
c) Digital milliammeter (current output measurement): 0 to 20mA.
Note. Resistance boxes have an inherent residual resistance that may range from a few m up to 1. This value must be
taken into account when simulating input levels, as should the overall tolerance of the resistors within the boxes.

7.2 Preparation

a) Switch off the supply and disconnect the conductivity cell(s), temperature compensator(s) and current output(s) from the
analyzer's terminal blocks.
b) Sensor A – Fig 7.1:
1) Link terminals B9 and B10.
2) Connect one terminal of the 0 to 10k decade resistance box to B13 and the other terminal to B14 to simulate the conductivity
cell. Connect the decade resistance box earth to B12.
3) Connect one terminal of the 0 to 1k decade resistance box to B9 and the other terminal to B11 to simulate the Pt100/
Pt1000.
Sensor B (dual input analyzers only) – Fig 7.1:
1) Link terminals B1 and B2.
2) Connect one terminal of the 0 to 10k decade resistance box to B5 and the other terminal to B6 to simulate the conductivity
cell. Connect the decade box resistance earth to B4.
3) Connect one terminal of the 0 to 1k decade resistance box to B1 and the other terminal to B3 to simulate the Pt100/Pt1000.
c) Connect the milliammeter to the analog output terminals.
d) Switch on the supply and allow ten minutes for the circuits to stabilize.
d) Select the
FACTORY SETTINGS
Sensor A Terminal Numbers
Sensor B Terminal Numbers
Fig. 7.1 Analyzer Terminal Links and Decade Resistance Box Connections
page and carry out Section 7.3.
Temperature
Simulator
B9
B10
B1
B2
Terminal link
B11 B12
B13
B14
B3
B4
B5
B6
Conductivity
Cell Simulator
Earth
61