Section 13
Testing functionality by secondary injection
13.5.3.2
13.5.4
13.5.4.1
178

Completing the test

Continue to test another function or end the test by changing the TESTMODE
setting to Off. Restore connections and settings to their original values, if they were
changed for testing purposes.
Four step residual overcurrent protection, (Zero sequence
or negative sequence directionality) EF4PTOC
Prepare the IED for verification of settings outlined in Section
to verify
settings".
Values of the logical signals for D2PTOC are available on the local HMI under
Main menu/Tests/Function status/Current protection/
ResidualOverCurr4Step(51N_67N,4(IN>))/EF4PTOC(51N_67N;4(IN>)):x,
where x = instance number.
The Signal Monitoring in PCM600 shows the same signals that are available on the
local HMI.

Four step directional earth fault protection

1.
Connect the test set for single current injection to the appropriate IED
terminals.
Connect the injection current to terminals L1 and neutral.
2.
Set the injected polarizing voltage slightly larger than the set minimum
polarizing voltage (5% of Ur) and set the injection current to lag the voltage
by an angle equal to the set reference characteristic angle (AngleRCA), if the
forward directional function is selected.
If reverse directional function is selected, set the injection current to lag the
polarizing voltage by an angle equal to RCA+ 180°.
3.
Increase the injected current and note the value at which the studied step of
the function operates.
4.
Decrease the current slowly and note the reset value.
5.
If the test has been performed by injection of current in phase L1, repeat the
test, injecting current into terminals L2 and L3 with a polarizing voltage
connected to terminals L2, respectively L3.
6.
Block lower set steps when testing higher set steps according to the
instructions that follow.
7.
Connect a trip output contact to a timer.
8.
Set the injected current to 200% of the operate level of the tested step, switch
on the current and check the time delay.
For inverse time curves, check the operate time at a current equal to 110% of
the operate current for txMin.
9.
Check that all operate and start contacts operate according to the
configuration (signal matrixes)
Generator protection REG670 2.2 IEC and Injection equipment REX060, REX061, REX062
1MRK 502 073-UEN A
SEMOD52967-24 v5
SEMOD53296-3 v9
"Preparing the IED
SEMOD53296-208 v7
Commissioning manual

Advertisement

Table of Contents
loading

Table of Contents