Section 10
Establishing connection and verifying the IEC 61850 communication
10.3
100

Verifying the communication

To verify that the communication is working a test/analyzing tool, for example
ITT600, can be used.
Verifying redundant IEC 61850-8-1 communication
Ensure that the IED receives IEC 61850-8-1 data on the selected Ethernet ports.
Browse in the local HMI to Main menu/Diagnostics/Communication/Ethernet
status/Access point/APStatusRedundant/RCHLCCH:1 and check that
ChARedStatus and ChBRedStatus are shown as Ok. Remove the optical
connection to one of the Ethernet ports. Verify that either signal status (depending
on which connection that was removed) is shown as Error and the that other signal
is shown as Ok. Be sure to re-connect the removed connection after completed
verification.
Generator protection REG670 2.2 IEC and Injection equipment REX060, REX061, REX062
1MRK 502 073-UEN A
SEMOD172108-24 v10
Commissioning manual

Advertisement

Table of Contents
loading

Table of Contents