Basic Ied Functions; Parameter Setting Group Handling Setgrps; Verifying The Settings - ABB REG670 Commissioning Manual

Generator protection, relion 670 series
Hide thumbs Also See for REG670:
Table of Contents

Advertisement

1MRK 502 073-UEN A
13.16
13.16.1
13.16.1.1
Generator protection REG670 2.2 IEC and Injection equipment REX060, REX061, REX062
Commissioning manual
Testing functionality by secondary injection
IEC07000188 V1 EN-US
Figure 66:
Test of RTC with I/O

Basic IED functions

Parameter setting group handling SETGRPS

Prepare the IED for verification of settings as outlined in section
test"
in this chapter.

Verifying the settings

1.
Check the configuration of binary inputs that control the selection of the
active setting group.
2.
Browse to the ActiveGroup menu to achieve information about the active
setting group.
The ActiveGroup menu is located on the local HMI underMain menu/Test/
Function status/Setting groups/ActiveGroup
3.
Connect the appropriate dc voltage to the corresponding binary input of the
IED and observe the information presented on the local HMI.
The displayed information must always correspond to the activated input.
4.
Check that the corresponding output indicates the active group.
Operating procedures for the PC aided methods of changing the active setting
groups are described in the corresponding PCM600 documents and
instructions for the operators within the SCS are included in the SCS
documentation.
Section 13
SEMOD52026-1 v1
M11369-2 v4
"Preparing for
M11369-4 v4
265