Commissioning
5
Commissioning
Users' qualification: Trained user
n
WARNING!
Sensor run-in periods
This can result in hazardous incorrect
metering
Take into consideration run in periods
when commissioning
–
Correct measuring and dosing is
only possible if the sensor is
working perfectly
–
It is imperative that the run in
periods of the sensors are
adhered to
–
The run in periods should be
allowed for when planning com‐
missioning
–
It may take a whole working day
to run-in the sensor
–
Please read the operating manual
for the sensor
Following completion of mechanical and
electrical assembly, the controller should
be integrated into the measuring point.
5.1
Initial commissioning
During initial commissioning the device's
display will be in "English". The display
will show "language english". Exception:
the language has been factory-preset to
the customer's requirement.
52
Start menu during initial commis‐
sioning
The "Language setting during initial
commissioning" menu appears only
once.
Later changes to the operating lan‐
guage can then be made via the
"General Settings/Information" menu
item.
language
Deutsch
english
Fig. 23: Initial commissioning display
This is followed by the selection of the
measured variable and the measuring
range in the "General Settings/Informa‐
tion" menu item.
5.1.1
Selection of the Operating
Language
With devices, which have not been pre‐
configured to the customer's specific
requirement, the operating language
required has to be selected in the "Gen‐
eral Settings / Operating Menu/" menu.
Ä Chapter 10.6 'General settings'
Refer to
on page 131