Unpacking; Pre-Installation Procedure - ABB IRB 1600 - 5/1.2 Product Manual

Articulated robot
Hide thumbs Also See for IRB 1600 - 5/1.2:
Table of Contents

Advertisement

2 Installation and commissioning

2.2.1. Pre-installation procedure

2.2 Unpacking

2.2.1. Pre-installation procedure
General
This instruction is primarily intended for use when unpacking and installing the robot for the
first time. It also contains information useful during later re-installation of the robot.
Checking the pre-requisites for installation
The check-list below details what must be observed before proceeding with the actual
installation of the robot:
Weight
The table below shows the weight of the robot model.
Robot model
IRB 1600 - x/1.2
IRB 1600 - x/1.45
38
Action
1. Make sure only qualified installation personnel
conforming to all national and local codes are allowed
to perform the installation.
2. Make sure the robot has not been damaged, by
visually inspecting its exterior.
3. Make sure the lifting device to be used is
dimensioned to handle the weight of the robot.
4. If the robot is not to be installed directly, it must be
stored.
5. Make sure the appointed operating environment of
the robot conforms to the specifications.
6. Before taking the robot to its installation site, make
sure the site conforms to applicable requirements.
7. Before moving the robot, make sure it does not tip
over!
8. When these prerequisites have been met, the robot
may be taken to its installation site.
Detailed in section:
Weight on page
Storage conditions on page
Operating conditions on page 39
and
Protection classes on page
39.
Loads on foundation on page 39
and
Requirements, foundation
on page
39.
Lifting robot with roundsling on
page
44.
Weight
247 kg
250 kg
Continues on next page
3HAC023637-001 Revision: B
38.
39.

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Irb 1600 - 5/1.45Irb 1600 - 7/1.2Irb 1600 - 7/1.45

Table of Contents