19) Install surge tank cover (1).
20) Install air cleaner upper case.
21) Connect coupler to intake air temp. sensor.
22) Install strut tower bar (1) and tighten strut tower bar mount-
ing bolts to specified torque.
Tightening torque
Strut tower bar mounting bolts
(a): 50 N·m (5.0 kg-m, 36.5 lb-ft)
23) Install fuse/relay box.
24) Check to ensure that all removed parts are back in place.
Reinstall any necessary parts which have not been rein-
stalled.
25) Refill cooling system, referring to "Cooling System Flush and
Refill" in Section 6B.
26) Connect negative cable at battery.
27) Upon completion of installation, verify that there is no fuel
leakage at each connection according to procedure
described in "Fuel Leakage Check Procedure" of Section 6-
1.