C-3 Status of BBM
D7 (Green): light when BBM activated
•
D8 (Green): light when BBM normal
•
D9 (RED): light when BBM charging
•
Note: The BBM status will be shown on the web browser of "Hardware Monitor Information" screen.
C-4 Installation
1. Make sure all power to the system is disconnected.
2. The 12Gb/s SAS RAID controller's battery connector is available for the optional battery backup module.
Connect the BBM cable to the 14-pin battery connector on the controller.
3. You can also use pre-drilled holes in their cabinet for securing the BBM using its three mounting positions.
4.
Low profile bracket also provided.
5.
The BBM will occupy one PCI slot on the host backplane.
C-5 Battery Backup Capacity
Battery backup capacity is defined as the maximum duration of a power failure for which data in the cache memory
can be maintained by the battery. The BBM's backup capacity varied with the memory chips that installed on the
12Gb/s SAS RAID controller.
104