8.4
Sliding the feed pipe into place
(carton of installation components)
The feed pipe (Fig. 24, [4]) comes in two parts for boilers
with 10 to 12 sections.
Pull the flat seal over the feed pipe (Fig. 24, [1]).
Insert the feed pipe from the front into the upper
boiler hub.
Close the pipe with a blanking flange (Fig. 24, [2]).
USER NOTE
The feed pipe must be correctly secured,
so that its exit ports are positioned at the
correct angle. This ensures optimum water
distribution in the area of the upper boiler
hub.
Ensure that the lugs (Fig. 24, [3]) on
the end plate of the feed pipe engage
into the recess of the upper boiler hub
(Fig. 24, [5]).
8.5

Seal-in the sensor well

Seal the sensor well R ¾" from the rear of the boiler
(length: 110 mm) into the R ¾" thread of the flow
connector (Fig. 25, [1]).
Logano GE515 - We reserve the right to make any changes due to technical modifications.
Boiler block assembly
3
4
5
2
1
Fig. 24 Install the feed pipe
Fig. 25 Install the sensor well