Leak Test - Buderus Logano GE515 Installation And Maintenance Instructions Manual

Oil- and gas-fired boilers
Hide thumbs Also See for Logano GE515:
Table of Contents

Advertisement

8
Boiler block assembly
8.6

Leak test

Carry out a boiler block leak test if the sections were
delivered loose. Pre-assembled sections are leak tested
in the factory.
For the further installation of pre-assembled boiler
sections (
chapter 11 "Burner installation", page 49).
8.6.1 Preparing the leak test
Close the lower boiler hub (Fig. 26, [3]) at the front
and rear. To do this, set the corresponding gasket
(Fig. 26, [1]) onto the respective boiler hub and
secure the blanking flange with 110 mm edge length.
The flange with internal thread (R ¾") for the fill and
drain connection (Fig. 26, [2]) is installed at the rear
of the boiler.
Fit the fill/drain cock (customer to flow).
Close the flow and return connections (install the
flange with vent screw on the flow connections).
SYSTEM DAMAGE
through overpressure.
CAUTION!
Ensure that no pressure, control or
safety equipment is fitted.
Slowly fill the boiler with water through the fill/drain
cock. Vent simultaneously at the air vent valve on the
boiler flow connection.
28
Logano GE515 - We reserve the right to make any changes due to technical modifications.
3
Fig. 26 Install the flange
1
2