2.4.4 Slide the return header into place (carton of
installation components)
Pull flat seal (
Fig. 19, [1]) over the return header
(
Fig. 19, [4]).
Insert the return header from the front into the upper
boiler hub.
Close the pipe with a blanking flange (
NOTE!
The profile (
of the feed pipe must engage into the
recess of the upper boiler hub (
[5]). This secures the feed pipe so, that the
feed pipe exit port is positioned at a right
angle to the boiler. This ensures optimum
water distribution in the area of the upper
boiler hub.
2.4.5 Sealing the sensor well
Sensor well ¾"
Seal the sensor well ¾" (Length: 110 mm)
(
Fig. 20, [1]) from above into the ¾" threaded hole
of the flow connection (
18
Fig. 19, [2]).
Fig. 19, [3]) on the end plate
Fig. 19,
Fig. 20, [2]).
Logano GE315 - We reserve the right to make any changes due to technical modifications
3
4
5
2
1
Fig. 19 Return header installation
Fig. 20 Sensor well installation