11 Burner installation

This chapter explains the main installation steps for
burners.
SYSTEM DAMAGE
through incorrect burner.
CAUTION!
Only use burners which meet the
technical preconditions of
Logano GE515 (
"Specification", page 10).
Close the burner door and secure with 4 bolts
(M16 x 140) (
chapter 8.8 "Installing boiler fittings
and the burner door", Fig. 32, [3] to [6]). Tighten the
screws alternately in a cross pattern.
Cut the steel insert plate (Fig. 66, [1]) on site using
oxy-acetylene or a drill according to the required
blast tube diameter (Ø max. 270 mm). Drill the
burner mounting holes according to the hole pattern
of the burner connection flange.
USER NOTE
Upon request, you may order pre-drilled
burner plates (accessory) from Buderus.
Secure the burner plate on the burner door with
screws provided (seal with GP packing cord
Ø 10 mm).
Screw the burner to the burner plate.
Cut out insulating rings according to the burner pipe
diameter (Fig. 66, [2]).
Fill the remaining gap between the thermal insulation
on the burner door and the blast tube (Fig. 66, [4])
with suitably adapted insulating rings (Fig. 66, [3]).
Connect the breather tube on the sight glass with the
burner to keep the glass free from condensation.
Logano GE515 - We reserve the right to make any changes due to technical modifications.
chapter 4
1
Fig. 66 Install the burner (dimensions in mm)
Burner installation
11
2
3
4