Hydraulic Connections; Flushing The System; Connection Of The Heating Circuit - REMEHA Quinta Pro 30 Installation And Service Manual

Wall-hung gas condensing boilers
Table of Contents

Advertisement

4. Installation
4.5

Hydraulic connections

20
4.5.1.
The installation must be cleaned and flushed according to BS 7593
(2006).
n Installing the boiler in new installations (installations
less than 6 months old)
4 Clean the installation with a universal cleaner to eliminate debris
from the appliance (copper, flaxen thread, flux).
4 Thoroughly flush the installation until the water runs clear and
shows no impurities.
n Installing the boiler in existing installations
4 Remove sludge from the installation.
4 Flush the installation.
4 Clean the installation with a universal cleaner to eliminate debris
from the appliance (copper, flaxen thread, flux).
4 Thoroughly flush the installation until the water runs clear and
shows no impurities.
Suitable chemicals and their use should be discussed with
specialist water treatment companies in respect to
aluminium heat exchangers.
4.5.2.
1. Remove the anti-dust plug located on the heating outlet
connection { under the boiler.
2. Connect the heating water outlet pipe to the heating flow
connection.
3. Install a filling and drainage valve on the installation for filling and
draining the boiler.
T002856-C

Flushing the system

Connection of the heating circuit

Quinta Pro 30 - 45 - 65 - 90 - 115
09/06/2011 - 123157-AF