4.4 Installation of the Temperature Compensation set

4.4.1 Mechanical Installation of the Temperature Compensation set

For the temperature compensation set there are three items, which need to be installed to guarantee a
proper functionality.
Upper telescope arm fixture, equipped with an IR sensor head, tilted mirror, air-purge unit, 15m
sensor cable and air-purge supply inlet hose
Lower telescope arm fixture as target (black counter paddle) for correct temperature reading
Aluminum die casting box for IR-Sensor to LAN connection
Please see chapter 3.1.2 until 3.1.4 for the dimensions and mounting points of the three items.

Figure 27: Upper and lower telescope arm fixtures installed after kiln exit

Figure 28: Schematic of kiln and deck outfeed arrangement