Commissioning Using Ion Setup; Configuring Metering Parameters - Siemens 9810 Series User Manual

Hide thumbs Also See for 9810 Series:
Table of Contents

Advertisement

9410 series - User manual
Parameter
Language

Commissioning using ION Setup

Use ION Setup to commission the meter for integration into your energy management system.
Connect to your meter using ION Setup then use the Setup Assistant to configure the meter.
Setup parameters are arranged in logical groupings and category folders.
Before exiting the Setup Assistant, ION Setup performs a meter configuration test and displays
the results. You can review the results and make changes as needed.
To turn off the meter configuration test:
1. Click Tools > Options.
2. Click the Assistant tab and clear the Configuration Checklist check box.
NOTE: ION Setup also performs a configuration test and displays results when configuring
certain features such as the Sag/Swell Logging wizard in the Power Quality Setup Assistant.

Configuring metering parameters

Use ION Setup to configure the meter's metering functionality.
1. Start ION Setup and open the Setup Assistant for your meter.
2. Configure the parameters in Metering Setup > Basic.
Basic tab
1
Demo mode is for demonstration only, and does not use the meter input terminals to display
values.
7EN05-0336-09
Parameter
Values
4W-WYE, DELTA, 3W-
Volts Mode
WYE, SINGLE, DEMO
PT Prim
1–999,999
PT Sec
1–999,999
CT Primary
1–999,999
CT
1–999,999
Secondary
Default value
English
Description
Power system type
1
Potential transformer's primary winding voltage
rating
Potential transformer's secondary winding
voltage rating
Current transformer's primary winding current
rating
Current transformer's secondary winding
current rating
Installation and commissioning
60