Mounting
5.4 Installation of UC 200
Securing the charging station
The charging station must be screwed to at least 3 of the 5 foundation fastening points on both
the right and the left side.
To secure the charging station, follow these steps:
1. Insert the fastening screws into the drill holes.
2. Tighten the screws.
Tightening torque: 70 Nm
5.4

Installation of UC 200

5.4.1

Inserting the connecting cable into the cabinet

After positioning the charging station on the base area for the first time, insert the power cable
into the charging station cabinet.
Danger to life when standing under lifted loads
If hoisting gear or load handling equipment fail, a lifted load can drop. If you are in the
hazardous area under or next to the lifted load at this time, death, serious injury and material
damage may result.
• Always use hoisting gear and load handling equipment properly.
• Do not stay in the hazardous area under or next to lifted loads.
Danger to life due to improper lifting
If you lift the charging station improperly, the device may tip over. Tipping of the charging
station can cause death, serious injury and material damage.
• Only qualified personnel should lift the charging station.
• Only use approved hoisting gear.
• Pay attention to the center of gravity of the charging station.
• Note the weight of the charging station.
• Only lift the charging station in a vertical position.
• The forks of the forklift must protrude on the opposite side of the charging station.
74
WARNING
DANGER
SICHARGE UC 100, UC 200, UC 300, UC 400, UC 600, UC 800
Operating Instructions, 10/2022, A5E50828019-AC