During commissioning, click "Stop" to stop commissioning and then click "Start" to continue
commissioning till commissioning ends. "Back" and "Skip" are provided in "10 ODU valves check before
startup". When an exception occurs in step 10, click "Back" to return to step 9 and then click "OK" in step
9 to perform commissioning again for step 10. If a U6 fault (valve exception) occurs in step 10, users can
click "Skip" to skip the fault. For other faults, "Skip" is unavailable.
In step "11 Select charging method", the system automatically selects manual or auto charging
mode. You can directly choose manual charging. If no operation is performed within 3 minutes, manual
charging is automatically entered.
GMV6 HR DC Inverter VRF Units Service Manual
38

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the GMV-VQ680WM/C-X and is the answer not in the manual?

Table of Contents