Gree
3.1.2 Files
To record the installation and commissioning of the unit, all the following documents need to be
prepared: minutes of the pre-commissioning scheme determining meeting, commissioning personnel
record form, pre-commissioning checklist, commissioning data record form, and commissioning report.
Minutes of the commissioning scheme determining meeting:
Minutes of the commissioning scheme determining meeting for XXX project:
Theme: xxx
Date: xxx
Place: xxx
Participants: xxx
Details: xxx
1
2
3
Checklist of the commissioning system appearance:
Item
Outdoor unit
Refrigerating
exchange box
system
Copper pipe
Condensate
Drainage system
Power cable
Power cable
Electrical system
Communication
cable material
Communication
Communication
system
Checklist of the equipment appearance of xxx air-conditioning project
Defect
appearance
Indoor unit
appearance
Mode
appearance
Hydro box
appearance
insulation
water pipe
insulation
diameter
layout
Air circuit
breaker
cable
connection
GMV6 HR DC Inverter VRF Units Service Manual
Inspector
16
Time

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the GMV-VQ680WM/C-X and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents