Transistor Tests - KEB COMBIVERT F5 Operation Manual

Elevator drive
Hide thumbs Also See for COMBIVERT F5:
Table of Contents

Advertisement

5.7.

Transistor Tests

The input and output circuits of the inverter can be checked externally with the inverter
power off and the motor leads disconnected by use of a multi-meter set to diode check.
i
Note: Different drive housings will have different readings. Measured values per
housing are given in tables below.
The inverter power must be de-energized and locked out for these tests! Disconnect
the mains wiring, motor wiring, and braking resistor from the inverter before taking
measurements.
Testing the rectifier, input circuit measurement
Positive Side
Negative lead of meter to positive DC terminal.
Positive lead of meter to L1/L2/L3 terminals.
+
+
+
-
Multimeter
Negative Side
Positive lead of meter to negative DC terminal.
Negative lead of meter to L1/L2/L3 terminals.
-
-
-
Multimeter
+
Transistor Tests
E, G, and H Housings
Measurement
To
Value
+
Terminal
L1
0.4 - 0.5
+ Terminal
L2
0.4 - 0.5
+ Terminal
L3
0.4 - 0.5
R, U, and W Housings
Measurement
To
Value
+ Terminal
L1
0.4 - 0.5
+ Terminal
L2
Open
+ Terminal
L3
Open
Measurement
To
Value
- Terminal
L1
0.4 - 0.5
- Terminal
L2
0.4 - 0.5
- Terminal
L3
0.4 - 0.5
Measurement
To
Value
- Terminal
L1
0.4
- Terminal
L2
0.4
- Terminal
L3
0.4
133